Skip to main content

Project - Electricity High Voltage

New HV connection on the 150kV / 6.6kV network

Description of the mission

  • Studies, design, detailed plans of the entire high, medium and low voltage electrical installation
  • Supply, manufacture and delivery of the various elements
  • On-site assembly
  • Commissioning
  • Assistance with project monitoring and plant needs

Goal of the overall project

New connection of the cement plant to the 150kV / 6.6kV grid of the Elia grid operator

Project details

Client activity

  • Extractive industry
  • Production of cements, aggregates and concrete

Solution brand

  • ABB